You are the project manager of an
environmental company that was hired to cleanup a historical arsenic
contamination site. Soil sampling results indicated the area impacted with
arsenic above action levels is 30 feet by 55 feet. The depth of the arsenic
plume is three feet below ground surface. The land owner wanted to clean this
site for future development. Using your textbook, answer the questions below to
help you prepare a cost estimate for this portion of the project. Your solutions and any assumptions to
justify your estimate must be shown.

1.  What
is the chemical symbol of arsenic, and what group/family does it belong to?

2.  Solve
for the minimum volume of soil that will be excavated in cubic yards?

3.  If
each dump truck can transport 18 cubic yards, determine how many dump trucks
loads will be transported? For calculation purposes, add a 15% “fluff factor”
(add to the volume that will be transported).

4.  If
the bulk density of soil is 1350 kg/m3 (84.3 lb/ft3), solve for the weight of
the soil that will be transported to a disposal site in kilograms?